PWD Building
1. NEW MEDICAL COLLEGE AT NALBARI under NLCPR Scheme
Agreement No. |
SMC/87/2018/28 Dated 10th Aug'2018. |
PROJECT VALUE |
A.A. value – 398.3122 Crore. Tender Value- 372.48 Crore |
Date of Commencement |
10.08.2018. |
Progress of work |
75 % |
Target of completion |
March’ 2023 |
Model Residential School at Nalbari (Barkhetri) under PMJVK
PROJECT VALUE |
3042.68 Lakh |
DATE OF Commencement |
13.10.2019 |
Progress of Work |
85 % |
Target date of completion |
Mar’ 2022 |
Outdoor Stadium Complex at Chamata Anchalik Krira Sangha at Chamata Nalbari (Signature Scheme)
PROJECT VALUE |
1000.00 Lakh |
DATE OF Commencement |
07.09.2019 |
Progress of Work |
87 % |
Target of completion |
Feb’ 2022 |
Block Development Office, Tihu (Signature Scheme)
PROJECT VALUE |
10 Crore |
DATE OF Commencement |
19.06.2019 |
Progress of Work |
36 % |
Target date of completion |
Mar’ 2023 |
ANM & GNM Nursing School at Mukalmua (Signature Scheme)
PROJECT VALUE |
10.00 Crore |
DATE OF Commencement |
06.07.2019 |
Progress of Work |
56% |
Target of completion |
Aug’ 2022 |
Indoor Stadium & Swimming Pool at Nalbari
The work has been withdrawn from the contractor, Md. Munnaf Ahmed vide office letter No. 4291 dated 21.06.2021
PROJECT VALUE |
4.04 Crore |
DATE OF Commencement |
Work withdrawn from the original contractor. |
Progress of Work |
0 % Allotment of balance work is under process. Work will started soon |
Target date of completion |
RCC 2 storied Prisoners’ Ward for 120 inmates at District Jail, Nalbari
PROJECT VALUE |
1.35 Crore |
DATE OF Commencement |
16.09.2019 |
Progress of Work |
62 % |
Target of completion |
Mar’ 2022 |
Augmentation of Govt Gurdon HS School, Nalbari under RIDF Scheme
PROJECT VALUE |
501.32 Lakh |
Date of Commencement |
12.12.2019 |
Progress of Work |
86.0 % |
Target Date of Completion |
January’2022 |
B. Ed College at Mugkuchi, Nalbari
PROJECT VALUE |
776.39 Lakh |
Date of Commencement |
04.12.2019 |
Progress of Work |
80 % |
Target Date of Completion |
Mar’2022 |
Upgradation of SMK Civil Hospital for Set up of ICU under Assam Critical Care Project 2020 at Nalbari
PROJECT VALUE |
1311.34 Lakh |
DATE OF Commencement |
25.11.2020 |
Progress of Work |
ICU- 100% Completed Residential part- Piling work is in progress. Overall 40 % completed. |
Target Date of Completion |
August’ 22 |
Sub Regional Science Centre cum Planetarium for ASTEC under Department of Science & Technology, Assam at Nalbari
PROJECT VALUE |
257.43 Lakh (Planetarium ) |
291.89 Lakh (Digital planetarium projection system) |
|
DATE OF Commencement |
05.11.2012 (Planetarium) 18.11.2020 (Digital Projection system) |
Progress of Work |
Planetarium 100 % completed. Digital Dome Installed. Furniture 100 % installed. Equipments of planetarium 60% completed. |
Target Date of Completion |
Jan’ 2022 |
Sub Regional Science Centre cum Planetarium for ASTEC under Department of Science & Technology, Assam at Nalbari
PROJECT VALUE |
204.86 Lakh (Residential part) |
DATE OF Commencement |
27.09.2018 |
Progress of Work |
Residential part 86 % completed. |
Target Date of Completion |
Jan’ 2022 |
New Engineering College at Ghograpar, Nalbari
PROJECT VALUE |
2466.30 Lakh |
F.W Order No. |
SMC/133/2020/30 08.06.21 |
Progress of Work |
20 % |
Target Date of Completion |
Dec’ 2023 |
Construction of 03 storied RCC I.B at Mukalmua under Barkhetri LAC in Nalbari
PROJECT VALUE |
318.775 Lakh |
Date of Commencement |
03.02.2021 |
Progress of Work |
18 % completed. Work upto plinth level completed. GF column casting is in progress. |
Target Date of Completion |
August’ 2022 |
Proposed construction of Inspection Bunglow (I.B) at Ghograpar in Nalbari District
PROJECT VALUE |
368.99 Lakh |
Work order Date |
24.09.2021 |
Progress of Work |
8 % |
Target Date of Completion |
Dec’2022 |
Establishment of Govt. Law College in 10 places of Assam
(at Tihu in Nalbari District)
PROJECT VALUE |
1474.00 Lakh |
Work order Date |
02.02.2021 |
Progress of Work |
15 % |
Target Date of Completion |
Mar’2023 |
Construction of proposed Office cum I.B for PWD Nalbari Rural Road Division , Nalbari
PROJECT VALUE |
274.515 Lakh |
Work order Date |
09.06.2021 |
Progress of Work |
Work not yet started |
Target Date of Completion |
Bottleneck: Work could not be started as the site has been changed and proposed to construct at the proposed Integrated Deputy Commissioner Office, Nalbari.