Fishery

Last Updated on: September 23, 2022

Ongoing Schemes

  • 1.Rural Infrastructure Development Fund (RIDF), 2018-19

Name of Scheme

No. of Beneficiary

Water Area (Ha)

Physical achievement

No. of Non Starter Beneficiary

No. of Beneficiary below 100% progress

Remarks

a) Individual Pond

313

44.28

294 Nos. (41.62 Ha)

3 Nos. (0.42 Ha)

16 Nos. (2.24 Ha)

 

As per progress report the allotted fund has been disbursed to the farmers Bank Account through NEFT/DBT by Director of Fisheries, Assam, Guwahati. And Rs 49100.00 refund from 3 nos non starter beneficiaries ,they surrendered

b) Community Tank

10

14.40

9 Nos. (13.40 Ha)

 

1 No. (1 Ha)

 

 

 

 

 

 

 

 

  • 2. Pradhan Mantri Matsya Sampada Yojana (PMMSY) 2020-21 

SL NO

Name of Scheme

No. Of Beneficiary

Water area (Ha)

Estimated amount (Lakhs)

Fund Utilized (Lakhs)

Balance Amount (Lakhs)

Remarks

1

Small Biofloc

1 No.

--

7.5 ( Govt.share3.00)

1.35

1.65

Progress is going on. (80%)

2

Boat & Nets Fishers

2 No.

--

10.0( Govt share 4.00)

1.80

2.20

Under Process

3

Cycle with Ice Box

15 Nos.

--

15.00 (0.80 Govt. Share)

0.117

0.683

Under Process

4

E-Rickshaw with Ice box

5 Nos.

--

10.00 (5.2 Govt. Share)

1.98

3.22

Progress is going on. (1 No. distributed)

5

FL stocking in wetland

3 Nos.

40

1.20 (0.64 Govt. Share)

0.2835

0.3565

Under Process

6

Integrated Fish Farming

21 Nos.

4.75

5.00 (2.6 Govt. Share)

1.17

1.43

Under Process

7

Livelihood support to fishers

1250 Nos.

--

56.25 (37.5 Govt. Share)

9.252

28.248

Under Process

8

Motor Cycle with Ice Box

3 Nos.

--

2.25 (1.22 Govt. Share)

0.3375

0.8825

Progress is going on. (1 No. distributed)

9

New Pond Construction -NEH

24 Nos.

6

50.4 (26.88 Govt. Share)

10.1115

16.7685

Progress is going on. (18 Nos. Completed)

10

Construction of Rearing Pond

21 Nos.

3

21.00 (9.22 Govt. Share)

3.96725

5.25275

Progress is going on. (15 Nos. Completed)

11

Large RAS

1 No.

--

50.00 (30.00 Govt. Share)

13.50

16.5

Progress is going on (60%)

12

Inputs for Fish Farming

24 Nos.

6

24 (12.80 Govt. Share)

3.33005

9.46995

Under Process

 

Total Fund required Rs.: 133.86 Lakhs

 

Fund Received Rs.: 59.2395 Lakhs

Fund Utilized Rs.: 47.1988 Lakhs

  • 3. Assam Agribusiness and Rural Transformation Project (APART) 2020-21 

Sl. No.

Name of Scheme

No. of Beneficiary

Water Area (Ha)

Fund received (Lakhs)

Fund Utilized (Lakhs)

Physical achievement

Remarks

1

Poly Culture Demonstration

129

32.6

33.00

32.6

100%

Fund sanction by ARIAS society, Govt. of Assam and accordingly released to Project Director, ATMA, Nalbari for subsequent released to beneficiary.

2

Paddy cum Fish Culture Demonstration

97

50.00

38.00

30.4

90%

3

Carp Prawn Poly Culture Demonstration

27

6.75

6.16

6.16

100%

4

Beel Fisheries

3

50.00

---

---

50%

Fund yet to released by ARIAS Society

  • 3. Assam Agribusiness and Rural Transformation Project (APART) 2021-22 

Sl. No.

Name of Scheme

No. of Beneficiary

Water Area (Ha)

Fund received (Lakhs)

Fund Utilized (Lakhs)

Physical achievement

Remarks

1

Poly Culture Demonstration

115

25

Nil

Nil

30%

 

 Fund yet to sanction by ARIAS society, Govt. of Assam

2

Paddy cum Fish Culture Demonstration

99

25

Nil

Nil

30%

3

Carp Prawn Poly Culture Demonstration

53

15

Nil

Nil

20%

4

Beel Fisheries

5

 

 

 

 

Survey is going on.