Power Department

Last Updated on: September 23, 2022

Name of Scheme: 1. DDUGJY-New

(Sanctioned Amount Rs. 53 Crore)

Item

Scope

Target date

Progress till date

BPL Beneficiary

10621 nos

31st December 2021

50%

11KV line

181.31 KM

3-ph LT line

162.29 KM

1-ph LT line

319.8 KM

63KVA DTR

194 nos

25 KVA DTR

116  nos

NAME OF SCHEME- 2. UDAY

(Sanctioned Amount Rs. 3.87 Crore)  

Sl.no.

Name of work

Progress

1

Construction of a new separate 11kV feeder at North Bank of NH31 under Nalbari Electrical Sub-Division-I ,Starting point: 33/11kV sariohtoli SS-NH31, Milonpur, Nalbari (Line Length : 3.65 KM)

 Completed

2

Construction of Terminal Equipment at 33/11 kV Soriohtali S/S for 11 kV  feeder under NALBARI ESD-I

 Work stopped due to Technical issue

3

Construction of 11kV Dedicated Feeder for DIC under Nalbari ESD-I (Line Length : 3.55 KM)

 Completed

4

Construction of 11kV Chamata Town feeder in order to bifurcate the existing 11kV Chamata feeder under Chamata Electrical Sub-Division (Line Length: 3.5 KM)

 Completed

NAME OF SCHEME- 3. AIIB Scheme 

AIIB 1st phase on going:

 

Sl. No

Site Location

Capacity of the 33/11 KV SS

Progress

1

Rampur

2*5 MVA

Land allotment pending at Circle Office

LOA issued

AIIB 2nd phase proposed:

 

Sl No

Site Location

Capacity of the 33/11 KV SS

Progress

1

Milan Bazar

2*5 MVA

Land allotment in process

2

Chatma

2*5 MVA

Land allotment in process

3

Barhelosa

2*5 MVA

Land allotment in process

4

Balitara

2*2.5 MVA

Land allotment in process

5

Pitpara

2*2.5 MVA

Land allotment in process

         

 NAME OF SCHEME- 4. Ashtadash Mukutor Unnoyonee Mala Scheme
(Sanctioned Amount Rs. 4.57 Crore)

Sl No

Type of School

No of un-electrified School

Progress

Targeted date

1

LP/UP

130

NIL

26.01.2022

2

Anganwadi Centre

1314

656

26.01.2022